Service Hotline:
0510-88700553/88707301
Cladding machine installation:
1, to determine the local operator 2-3, the equipment should be installed in a clean environment, the ground level of the workshop. Equipment in place, remove the attachment on the machine, packing list inventory, verification.
2, adjust the anchor bolts, so that uniform force, so that the body to reach the level of state.
3, check the equipment in transit bump damage.
4, Power: The machine uses 380V three-phase four-wire power supply. The power cord should be greater than 2.5mm & sup2 ;, the right of the power into a line for the zero line. This machine according to the grounding standard installation ground wire. Turn on the power to check if the motor, heater, lighting, etc. are normal.
debugging:
1, profile positioning: Take a good profile, requirements: can not be bent or distorted, on the bed conveyor wheel, according to profile width, shape and coating requirements, adjust the distance between the two rows of conveyor wheels ; Adjust the width and height of the abutment and the platform to make it suitable for cladding requirements; Install the guide wheels on both sides so that the profiles and the transport wheel parallel to the direction of movement.
2, the installation and adjustment of the pressure wheel: According to the contour profile of the profile to install a small pressure wheel adjustment, the general choice profile centerline or section, the outline of the main curve of the highest point or the lowest point, along the profile contour point by point transition, rolling. The profiles and membrane compound together. Install a small pressure wheel to force the balance line, so at the same time. Pressure wheel above, the bottom must be installed bearing wheel, so that the balance of the force around the top and bottom. Otherwise it will make the line joints appear false and so on. Large plane, small pressure roller can be used from the center gradually rolling to the two sides of the transition, at 90 ° corner need to use a small pressure roller 3 times gradually turn angle. Complex shapes of lines, small pressure wheel to be arranged in nature, can not be forced to shape. In particular, the decorative paper stickers, it should be more natural and fluid.
3, plastic box or roller coating system
⑴, cold plastic box operation method:
①, the unloading method of plastic boxes: a smooth rubber tank up, plastic boxes naturally from the platform.
②, glue layer thickness adjustment: the lower part of the glue box on both sides of the lower bolt can be adjusted to adjust the thickness of the glue layer.
⑵, roller coating device use:
Rotate the squeegee shaft on the cartridge to adjust the thickness of the coating. Turn the adjustment handle, clockwise rotation, thick plastic layer; counterclockwise rotation, the thinning of the adhesive layer. Until the glue evenly.
4, diaphragm installation and glue adjustment
The good cut film installed on the shaft hanging film, adjust the position, the plastic box off, the diaphragm through the film guide roller, through the bottom of the plastic box gap, glue added to the plastic box, opened the diagonal iron, The distance is slightly narrower than the width of the diaphragm. Adjust the screws on both sides of the front of the plastic box to control the thickness of the glue. Glue thickness according to the type of glue may be, generally 50-100 grams per square meter of glue.
Copyright ◎ 2016 yudajixie.com Wuxi Yuda Light Industry Machinery Factory All rights reserved suICP12031851suICP12031851